: 在來灌水吧
: 給你們pmp情境題
: During activity definition, the team discovers that they do not know enough
: to define that activities for 30% of the work packages.
: What would be the BEST course of action?
: a. redo scope definition
: b. review the project charter with the sponsor and them
: c. Continue on to activity sequencing and define the activities at a later date
: d. Include this probelm as part of risk identification.
---------------
與題目無關恕刪
---------------

這題很久了被我挖出來 XD
不知道有沒有人可以提供觀點討論一下

我其實看完選了C
因為覺得應該用rolling wave的想法 分階段做

不過先前討論答案都是B或D
有人願意分享一下嗎?

--

All Comments

Skylar DavisLinda avatarSkylar DavisLinda2009-11-05
C 會有做白工的危險性
Emma avatarEmma2009-11-06
且工作內容定義不清 職責也不易分清楚
Poppy avatarPoppy2009-11-08
看案子的狀況。主要是客戶的情況與案子的進度。客戶好溝通,
Callum avatarCallum2009-11-10
就走b。客戶不好溝通或是自己的談判能力強,就選D。
Rebecca avatarRebecca2009-11-11
無法定義可交付成果的原因可能來自於範圍不夠清楚