Which of the following is the MOST likely cause of poor risk management ?
A: Inadequate risk response planning.
B: Poor risk monitoring and control.
C: Lack of a prioritized list of risks.
D: Lack of detail in the scope statement.
There is a probability of 0.10 that a given risk will occur in a project.
If it occurs, it will result in a loss of US $10000.
The insurance cost for this event is US $700,
with a deductible amount of US $250.
Should a rational project manager buy this insurance ?
A: Yes, since US $1000 is greater than US $950.
B: Yes, since US $1000 is greater than US $700.
C: No, since the deductible amount changes the expected value of the risk
event.
D: No, since US $1250 is greater than US $ 1000.
這題答案跟我選的不一樣,但我腦筋轉不出來....
一整個不明白為什麼.....
--
Tags:
PMP
All Comments

By Eden
at 2009-05-27T21:35
at 2009-05-27T21:35

By Daph Bay
at 2009-05-29T07:58
at 2009-05-29T07:58
Related Posts
PMP 職業道德考題疑問 (答案)

By Sandy
at 2009-05-23T15:33
at 2009-05-23T15:33
PMP 職業道德考題疑問

By Joe
at 2009-05-23T14:31
at 2009-05-23T14:31
PMP 職業道德考題疑問

By Ida
at 2009-05-23T13:40
at 2009-05-23T13:40
奧美廣告公關公司

By Lauren
at 2009-05-20T21:48
at 2009-05-20T21:48
100-p幣 請任主管級的朋友幫忙

By Quanna
at 2009-05-19T15:30
at 2009-05-19T15:30