關於輸入與輸出還有工具的選擇題 - PMP
By Candice
at 2010-03-19T15:32
at 2010-03-19T15:32
Table of Contents
要麻煩各位大大了
謝謝><
Q: you create an itinerary on a travel web site. you'll use the iutinerary
when you board your flight.
a)input b)tool c)output
A: a,c
Reason: the itinerary was an output of the Develop Project Management Plan
process but an input to the Direct and Manage Project Work process.
我以為是b
有點不太了解他要表達的涵義
(第一次po文 有冒犯處請原諒)
--
謝謝><
Q: you create an itinerary on a travel web site. you'll use the iutinerary
when you board your flight.
a)input b)tool c)output
A: a,c
Reason: the itinerary was an output of the Develop Project Management Plan
process but an input to the Direct and Manage Project Work process.
我以為是b
有點不太了解他要表達的涵義
(第一次po文 有冒犯處請原諒)
--
Tags:
PMP
All Comments
Related Posts
由誰報價?
By Dora
at 2010-03-19T00:14
at 2010-03-19T00:14
博鴻專案管理每週充電報
By Hazel
at 2010-03-17T12:08
at 2010-03-17T12:08
博鴻線上講座3pdu & PMP課程免費旁聽
By Ingrid
at 2010-03-17T10:02
at 2010-03-17T10:02
空白分析? white space analysis?
By Mia
at 2010-03-16T22:05
at 2010-03-16T22:05
消息分享,台北大學就業博覽會!
By Hedwig
at 2010-03-16T21:04
at 2010-03-16T21:04